Service Specification

Heavy Lifting

Heavy lifting services for loads from 10 tons to 1,000+ tons, including engineered lift plans, specialized equipment, and certified crews for construction, energy, and industrial projects.

Get a Free Quote

Common Deployments

  • Hydraulic gantry lifts
  • Strand jack operations
  • Jack-and-slide systems
  • SPMT heavy transport
  • Tandem and multi-crane lifts

Critical Parameters

Our matching team reviews these project details to route your request to the right crews.

01

Project Scope & Load Data

Load weight, dimensions, center of gravity, pick and set locations, site access constraints, and any environmental or schedule requirements that define the lift.

02

Lift Engineering

PE-stamped lift plan with crane or equipment selection, rigging design, ground bearing analysis, FEA where required, and contingency procedures for the specific load and site.

03

Crew & Equipment Matching

Contractor selection based on equipment availability, capacity ratings, geographic proximity, and documented experience with comparable heavy lift projects.

04

Execution & Verification

Lift execution under the engineered plan with load monitoring, signal communication, and post-lift placement verification against project specifications.

Heavy lifting services encompass the planning, engineering, and execution of lifts that exceed the capacity of standard rigging operations. When loads reach tens, hundreds, or thousands of tons, standard mobile cranes and conventional rigging methods give way to specialized equipment and engineered solutions. Every heavy lift project in our network is executed under a PE-stamped lift plan and complies with OSHA 29 CFR 1926 Subpart CC (Cranes and Derricks in Construction) and the applicable ASME B30 safety standards for the equipment involved.

What Makes a Lift “Heavy”

The term “heavy lift” has no single regulatory definition, but the industry draws a practical line where standard crane rigging methods reach their limits. Loads exceeding 75% of a crane’s rated capacity trigger OSHA’s critical lift requirements under 29 CFR 1926.1432, which mandate additional planning, supervision, and safety protocols. Beyond that threshold, loads requiring multiple cranes, engineered rigging attachments, or non-standard lifting systems such as gantries and strand jacks all fall squarely into heavy lift territory.

Capacity ranges in heavy lifting span from approximately 10 tons (where industrial rigging transitions into engineered heavy lift work) to well over 1,000 tons for the largest strand jack and SPMT operations. The defining characteristic is not the weight alone — it is the engineering rigor required to execute the lift safely.

Heavy Lift Methods and Equipment

Each heavy lift method is suited to specific load characteristics, site conditions, and project constraints. Selecting the right approach is an engineering decision that balances capacity, precision, schedule, and cost.

Hydraulic Gantry Systems

Hydraulic gantries governed by ASME B30.1 (Jacks, Industrial Rollers, Air Casters, and Hydraulic Gantries) are the workhorse of indoor and confined-space heavy lifting. Individual gantry legs range from 75 to over 1,000 tons capacity, and multi-leg configurations can handle combined loads of several thousand tons. Gantries lift, travel, and place loads within tight footprints — making them essential for manufacturing plant installations, power generation equipment, and retrofit projects where crane access is limited.

Strand Jacks

Strand jacks lift loads by pulling high-strength steel strands through hydraulic cylinders, achieving capacities from 100 to over 5,000 tons per unit. Multiple strand jacks can be synchronized for lifts exceeding 10,000 tons. This method is common in petrochemical plant construction (setting reactor vessels, columns, and heat exchangers), bridge construction (incremental launching and segment lifting), and offshore platform module installation.

Jack-and-Slide Systems

Jack-and-slide combines vertical hydraulic jacking with horizontal skidding on PTFE (Teflon) slide paths. This method positions heavy loads laterally onto foundations, bridge piers, or equipment pads without crane involvement. It is frequently used for bridge superstructure placement, transformer installation at substations, and industrial equipment that must be slid into position within existing structures.

SPMTs (Self-Propelled Modular Transporters)

SPMTs are computer-controlled multi-axle platform transporters that combine transport and precision placement. Each module has independently controlled axle lines with hydraulic suspension, and modules can be combined into arrays handling loads exceeding 10,000 tons. SPMTs are governed by site-specific engineering rather than a single ASME standard, and they are the equipment of choice for moving prefabricated modules in petrochemical, LNG, and power generation construction.

Tandem and Multi-Crane Lifts

When a single crane cannot handle the load, two or more cranes work in coordination under a single engineered lift plan. OSHA 29 CFR 1926.1432 classifies multi-crane lifts as critical lifts requiring a qualified person to develop and oversee the operation. Load sharing, swing coordination, and communication protocols must be documented and rehearsed. Tandem lifts are common for bridge beams, large structural steel assemblies, and mechanical equipment that exceeds single-crane capacity.

Industries Served

Heavy lifting services support projects across multiple sectors:

  • Construction — Setting structural steel, precast components, and mechanical equipment on commercial, institutional, and infrastructure projects. See our crane rigging services for standard construction lifts.
  • Energy and Power Generation — Turbine sets, generator stators, boiler components, and transformer installations at fossil fuel, nuclear, and renewable energy facilities.
  • Petrochemical and Refining — Reactor vessels, distillation columns, heat exchangers, and modular process units that routinely exceed 500 tons.
  • Manufacturing — Heavy press installations, CNC and production line equipment, and plant expansions requiring precision placement within operating facilities.
  • Infrastructure — Bridge segments, tunnel boring machine components, lock gates, and water treatment equipment.

Engineering Requirements

Heavy lifts demand a level of engineering analysis that distinguishes them from standard rigging operations:

  • PE-stamped lift plans — Required for all critical lifts under OSHA 29 CFR 1926.1432. The lift plan documents load data, equipment selection, rigging configuration, operational procedures, and contingency measures. A Professional Engineer licensed in the project’s state seals the plan.
  • Finite Element Analysis (FEA) — Non-standard lifting lugs, spreader beams, and temporary support structures require FEA to verify stress distribution and confirm adequate safety factors. AISC Design Guide 29 (Vertical Bracing Connections) and AWS D1.1 (Structural Welding Code) govern the design and fabrication of steel lifting attachments.
  • Ground bearing studies — Crane outrigger loads and gantry reactions concentrate massive forces onto small areas. Geotechnical analysis confirms that soil bearing capacity and any temporary foundations (timber mats, steel plates, or engineered pads) can support the imposed loads without settlement.
  • Rigging engineering — Sling angles, shackle ratings, and hardware selection per ASME B30.9 (Slings) and ASME B30.26 (Rigging Hardware) must account for dynamic load factors, side loading, and the specific geometry of each pick.

Safety Protocols for Heavy Lifts

Heavy lift safety goes beyond standard rigging protocols. The consequences of failure scale with the load — a dropped 500-ton vessel is a catastrophic event, not a near-miss. Key safety requirements include:

  • Pre-lift engineering review with all parties (contractor, owner, engineer of record) reviewing the lift plan, contingency procedures, and stop-work criteria
  • Load monitoring systems including load cells on crane hooks and gantry legs that provide real-time weight data during the lift
  • Weather protocols with documented wind speed limits (typically 20–25 mph for heavy lifts, lower for high-profile loads) and suspension criteria
  • Exclusion zones cleared of all non-essential personnel during the lift, with barricading per the lift plan
  • Communication protocols using dedicated radio channels with qualified signal persons per OSHA 29 CFR 1926.1428

Contractors in the Specialized Carriers & Rigging Association (SC&RA), an international trade association of more than 1,400 members across 46 countries, follow industry best practices for heavy lift safety and maintain the specialized insurance, engineering capabilities, and equipment certifications these projects demand.

Our Matching Process

Heavy lift projects require contractors with specific equipment, engineering depth, and a documented track record on comparable jobs. We match you with heavy lift specialists based on your load weight, lift method, geographic location, and project timeline. Every contractor in our network maintains current OSHA compliance, appropriate insurance limits for heavy lift work, and demonstrated experience with the equipment and methods your project requires. Whether your project involves a 50-ton tandem crane lift or a 2,000-ton strand jack operation, we connect you with qualified crews who have done it before. For projects that also require over-the-road transport of heavy components, see our heavy haul services.

Operational FAQ

What qualifies as a heavy lift?

There is no single regulatory threshold, but the industry generally classifies any lift requiring an engineered lift plan due to load weight, complexity, or risk as a heavy lift. In practice, this typically means loads exceeding 75% of a crane's rated capacity (the OSHA critical lift threshold under 29 CFR 1926.1432), loads requiring multiple cranes, or loads that exceed the capacity of conventional mobile cranes and require specialized equipment such as hydraulic gantries, strand jacks, or SPMTs. The Specialized Carriers & Rigging Association (SC&RA) defines heavy lift projects as those requiring detailed engineering analysis beyond standard lift planning.

How much do heavy lifting services cost?

Heavy lift costs vary widely based on load weight, lift method, engineering complexity, and site conditions. A tandem crane lift for a 50-ton mechanical unit may cost $15,000 to $50,000, while a strand jack operation for a 500-ton reactor vessel can exceed $500,000. Key cost drivers include the number and size of cranes or gantry systems required, PE-stamped engineering and FEA analysis, ground preparation and temporary foundations, and mobilization distance. Contact us for a free quote on your specific project.

What equipment is used for heavy lifts?

Heavy lift equipment is selected based on load weight, geometry, and site conditions. Common systems include hydraulic gantries (ASME B30.1) with capacities from 75 to over 1,000 tons per leg, strand jacks capable of lifting thousands of tons by pulling steel strands through hydraulic cylinders, SPMTs (self-propelled modular transporters) that combine transport and lifting in a single operation, jack-and-slide systems for horizontal moves of heavy loads onto foundations, and tandem crane lifts using two or more cranes under a single engineered lift plan per OSHA 29 CFR 1926.1432 multi-crane lift requirements.

Do you provide engineered lift plans?

Yes. Every heavy lift in our network requires a PE-stamped (Professional Engineer-stamped) lift plan before execution. This is both an industry best practice and a regulatory requirement for critical lifts under OSHA 29 CFR 1926.1432. Lift plans include load calculations, rigging hardware specifications, crane or equipment configuration, ground bearing analysis, FEA (finite element analysis) for non-standard lifting attachments, and step-by-step procedures. Our matched contractors either maintain in-house engineering teams or work with third-party PE firms who specialize in heavy lift engineering.

Common Questions

Start Your Project

Submit your heavy lifting project details for a free quote.

Get a Free Quote

Zero Obligation. 100% Free.